Causes of slow and low disbursement in donor funded projects in Sub–Saharan Africa: evidence fromUganda

Abstract

In this paper, we document the experience with donor-funded projects in Uganda, identifying both factors that contributed to their success and those that hindered their effectiveness.

Key findings on disbursement problems:

We find that the problem of low or slow disbursement is associated with funds procedures and conditions attached to specific projects, including:

counterpart funding requirements;

conditions for aid effectiveness;

deficiencies in procurement planning; and

failure to follow the conditionality and funding guidelines on procurement procedures.

The ranking of these problems varies from project to project.

Capacity constraints:

Weak project implementation capacity (capacity constraints) implies that attention needs to be focused on building the capacity of technical staff, especially in those projects with elaborate procedures such as the World Bank IDA/IBRD projects.

We are a leading independent, nonpartisan research organization dedicated to advancing evidence-based policy solutions for sustainable economic development in Africa.

Subscribe to our Newsletter

Stay connected with IPRA’s quarterly newsletter featuring the latest news, book releases, and original content.

Newsletter Form (#4)

Become a Non-Resident Fellow

Copyright © 2025 Institute of Policy Research and Analysis. All rights reserved.